A designed solution with added value, Sønderborg, Denmark
A designed solution with added value
In autumn 2014, Uponor Infra in Denmark was contacted by the utility company Sønderborg Forsyning in the southern part of Jutland. They were originally looking for a solution to replace an existing 1,000mm concrete pipeline, but ended up with a designed solution with added value.
Project facts
Uponor Involvement
“The pipeline went through a privately owned field and of course the owner was not too happy with the overflow. In addition, the field owner did not wish to have a pipeline going through his field. The pipe would thus have to be installed along the field boundary. Therefore, we turned to Uponor for a designed solution.”
A welded designed solution
“In the solution proposal, we concentrated on the customer’s need for a designed and welded solution in order to tackle the challenges posed by the height differences along the field. The height differences and the terrain meant that we had to take a lot of bends into account. Our original solution was based only on SN8 Weholite pipes, but we revised it later on during the project, as we could offer the customer a far better solution yielding greater value,” says Jan Lunding, Project Technical Manager at Uponor Infra.
During the proposal process, Uponor worked together with Grontmij, one of the leading consulting and engineering companies in Europe, in delivering, for instance, the method statement for installation guidance.
Added value, easy and fast installation
During the evaluation of the proposed solution, which took place at the construction site, Jan Lunding discovered that the Weholite pipeline would be connected to a concrete chamber at one end. The chamber had to be replaced. Uponor suggested that the chamber should be made of plastic instead of concrete. Calculations were made and sent to Sønderborg Forsyning. Within a week, the order was placed!
“The chamber was made of Weholite panels. It gave us added value by saving us a lot of time. Since the chamber could be prefabricated and delivered in one piece, it was easy and fast for the constructor to install. Time was an important issue for us, especially as the pipeline and chamber are intended to transport stormwater away from the area,” says Finn Christensen.
A professional and active partner
“Uponor not only provided us with a customised solution, but also offered a range of services and technical support,” says Finn Christensen.
“With Uponor we had a professional and active partner throughout the entire project. Therefore we ended up with a unique solution that matched our specific needs for a welded designed solution. Furthermore, we saved time on the project, because Uponor could provide us with a chamber that was ready to be installed right away. I’m really looking forward to working with Uponor’s designed solutions department on future projects,” says Finn Christensen.
We saved time on the project, because Uponor could provide us with a chamber that was ready to be installed right away.
Project information
Project information
Similar projects
Pump structure secures stormwater system’s long life
Drinking water passing through contaminated area in Thisted
Intake pipeline for seawater in Copenhagen Harbour
Butt welding by night of 900 mm pipes ensures stable operation of a district cooling solution in Copenhagen Harbour.
TV-Tower, Estonia
Heavy-duty pipe for Tallinn’s district heating network
PE pressure sewer system from Harjavalta to the city of Pori
New Uponor IQ –Storm water system - Sustainability and Quality in Road Infrastructure
Ultra Double replace concrete pipe line in Raahe
ProFuse pressure pipe line provides drinking water to cottage owners in islands near by Uusikaupunki
Environmental friendly heating and storm water systems in new Launonen day-care centre
New water pipeline
Hybrid solutions for storm water management
City of Lahti is building new neighborhood called Ranta-Kartano. While they were constructing basic infrastucture the city saw the possibilty to reserve some ground space for storm water management. Now there is a test running for different kind of storm water management. Uponor is involved with new type of storm water filter.
An easy and reliable storm water solution
Now that’s truly FAST
Handling storm water in a smart way
Flow measurement reveals leaks in the water supply network
Fire wastewater safely recovered
Secure tunnel trunk lines
Life is grand for graylings in the pure waters of Ounasjoki River
Europe’s largest ever plastic culvert goes to Norway
Don’t count on luck to protect you from flooding
Water treatment plant
Urban runoff under control – quickly and easily
Relining to the rescue in Kajaani
Clean drinking water for 17,000 scouts
Iisalmen Vesi renovated a trunk line by relining
To rebuild an office building located in the heart of Amsterdam into 150 appartments in a relatively short time is definitely a big challenge.
Quick installation in the Konotopa channel
Weholite limits overflows and pollution in London
Fighting against an ecological disaster in a world-record time
Rapid action was critical when a sewage collector broke in Warsaw, Poland, causing a massive waste spill into the Vistula River. Uponor Infra’s crew worked 24 hours a day in order to stop the pollution of the river. A temporary pipeline was produced, delivered and connected in just eight days.
A smart retention system for an anti-flooding solution
September 2018 saw the launch of the project for a stormwater drainage system in Rzeszów, almost 26 kilometres long, in the residential District of Budziwój, which partially coincides with the floodplain of the River Wisłok. One of the elements of this system is the retention canal. The project, scheduled for delivery by May 2020, will help to finally solve flooding problems which have been plaguing the residents of this region of Poland.
Sewage pipelines to sewage treatment plant - HDD method
Collectors for sewage treatment plant
Renovation of reinforced concrete sewer - relining method
Sewage retention chanel
Renovation of cast iron water supply pipeline - swagelining
Thanks to swagelining technology, it was possible to carry out most of the water line modernisation works in the centre of the city of Łódź, in a built-up area, along traffic lanes with heavy traffic of motor vehicles and trams.
Sea outlet - discharge of stream water into the Gdańsk Bay
Sea outlet - discharge of stream water into the Gdańsk Bay part 2
Renovation of damaged stoneware collector – cracking/short relining
Sewage separation system
Construction of storm water collectors in Nowe Polkowice is one of the stages of a big investment concerning the drainage of the district.
Sea outlet of treated wastewater
A sea outlet of treated wastewater was initiated in Swarzewo. It is yet another of the many environmentally friendly projects that have recently been carried out in Poland where PE pipes were used.