Uponor North America
5925 148th Street West
Apple Valley, MN 55124
Caso de estudio

Auron, München, Germany

Auron

Datos del proyecto

München, Germany
Office building
Climatización Invisible
Completion: 2010

Participación de Uponor

39000
The first construction phase of the AURON office building was awarded a Green Building Gold certificate according to the provisions of the Deutsche Gesellschaft für Nachhaltiges Bauen (DGNB) [German society for sustainable building].


The Uponor Contec ON concrete surface activation heats and cools approximately 39,000 m² of floor space highly efficiently using regenerative energies. As a consequence, the system complies with the requirements relating to sustainability and high heating and cooling performance levels. The system also helps to improve the interior design as no radiators are required in the rooms. This means that there were no restrictions regarding the internal architecture, allowing Feng-Shui principles to be applied. The principals, Employrion Immobilien GmbH & Co. KG, a project company belonging to Accumulata Immobilien Development GmbH, and LBBW Immobilien GmbH, were especially impressed with the fact that Uponor Contec ON can be installed in a monovalent manner.


The Contec ON system is supplied with heat using a groundwater heat pump as well as from a district heating station. For heating, a flow of 32 °C and a return of 28 °C were selected. Using these parameters, the thermo-active ceiling achieves a heating performance of 60 W/m², and 53 W/m² in what is known as the drill-proof area.


Cooling units utilize the water from the well to cool the building. The system achieves a cooling performance of 70 W/m², and 63 W/m² in the drill-proof area. Contec ON is installed close to the surface, so compared to conventional concrete core activation this system offers a faster response. This means that the temperature of each of the units sized between 200 m² and 400 m² can be individually controlled. On the top floor of the seven-story building, Contec ON modules were installed in two different material qualities: on well-proven plastic mats and on special metal mats.


The required grid spacing of the elements was prefabricated in the factory. This ensures the necessary heating and cooling capacity and facilitates swift construction as the precise position of the heating and cooling pipes with respect to height is already guaranteed during the assembly phase. For the Contec ON modules equipped with metal mats, a pipe clearance of only 10 cm was selected. The Contec ON mats were placed directly on the control panels, and the system of pipes was routed axially with a clearance. Thanks to this design, partition walls can be optionally installed in the intermediate spaces.


In the area close to the building facade, Contec ON was routed at a distance of approximately 20 mm from the lower edge of the ceiling with a pipe clearance of 85 mm. This allows for fast supply and removal of heating and cooling loads, resulting in quick and efficient temperature control. The system delivers about 50 percent of the planned heating and cooling output in 30 minutes. For the areas inside the offices and on the corridor side of the floors of the building, the system was installed with a drilling safety clearance of 60 mm from the lower edge of the ceiling.


The routing clearance is 100 mm. In these drill-proof areas, 50 percent of the heating and cooling output is reached after approximately 60 minutes. In rooms with special requirements, such as corner offices, cooling elements supplement the Contec ON system. The elements are connected via additional thermal socket outlets from Uponor.
 

Auron

0002980

Información del proyecto

Información del proyecto

Address
Landsberger Straße
Country
Germany
Completion
2010
Project Type
New building
Building Type
Office building
Product lines
Contec ON

Similar projects

Bayer Qingdao ECB Lighthouse

Bayer Qingdao ECB Lighthouse

ECB Lighthouse, which serves as the administration building of a Bayer MaterialScience plant in Qingdao, is the first building in China of the Bayer Eco Commercial Building (ECB) Program.
The installation of Uponor storm water cassettes in Shopping Center Karisma, Lahti

The installation of Uponor storm water cassettes in Shopping Center Karisma, Lahti

In November 2011 one of the largest shopping centers of Finland was opened in Lahti. The Karisma shopping centre is one of Finland´s largest shopping centers measured by sales area and number of stores. Developer of Karisma is Kesko. Construction of Karisma has been one of the biggest investments ever in retail trade of Kesko. The main contractor of Karisma was SRV Rakennus ltd.
Day-care centre to be built with energy piles

Day-care centre to be built with energy piles

As requested by the City of Vantaa, the Vaaralanpuisto day-care centre has been planned based on the "nearly 0 energy days" concept. Construction work for the day-care centre began in late summer 2016, and the project will be completed in July 2017. Project costs are estimated at EUR 5.4 million, and the day-care centre will accommodate about 130 children. Among the various energy production options available for the site, the City of Vantaa chose the energy pile and solar thermal collector system jointly developed by Uponor and Ruukki.
Klimahaus Bremerhaven 8°

Klimahaus Bremerhaven 8°

The Klimahaus Bremerhaven 8° Ost in Germany is a science centre that presents climate and climate change topics in a comprehensible scientific manner.
Berliner Bogen

Berliner Bogen

Berliner Bogen in Hamburg – cutting-edge architecture combined with state-of-the-art technology
Energy Efficiency Center

Energy Efficiency Center

The foyer, information centre and conference room at the Energy Efficiency Centre in Würzburg uses the Uponor Klett line for energy-efficient radiant heating and cooling.
Ericusspitze Spiegelhaus

Ericusspitze Spiegelhaus

New company HQ of the Spiegel Group is located at the Ericusspitze. The concrete core activation from Uponor ensures pleasant temperature levels in the building.
Kranhaeuser

Kranhaeuser

Fantastic, modern architecture directly on the Rhine in Cologne - the Kranhaus buildings
Brain Box Berlin

Brain Box Berlin

Thermal concrete core activation with Uponor Contec provides economical, energy-efficient and sustainable building temperature control in the new landmark Adlershof Science and Technology Centre.

 

Leitradlofts, Cologne

Leitradlofts, Cologne

A hygienically optimal drinking water installation was integrated into the new office complex – thanks to Uni Pipe PLUS within a very short time.

First Uponor Comfort Panel project in Hungary

First Uponor Comfort Panel project in Hungary

An office building, where proper comfort is provided for doing your job The commercial buildings provide more or less limited space as the workplace for people. Therefore cooling the air is an important factor in maintaining their comfort during their stay. In order to keep the daily work undisturbed, the system used should be installed easily, should be efficient economically, and should be hygienic.
Immeuble Delta Green

Immeuble Delta Green

La dalle active Uponor est intégrée depuis 2017 dans l’immeuble Delta Green, bâtiment tertiaire de 4600m2 comprenant 4 niveaux. Celui-ci est le premier bâtiment de la région tout à fait autonome en énergie.

Standard Bank

Standard Bank

Uponor PE-Xa pipe used for refurbishment of chilled water pipelines in the head office of South Africa's Standard Bank located in Johannesburg.
Palazzo Ferrazzi - Brescia

Palazzo Ferrazzi - Brescia

Uponor brings the comfort of its Underfloor Heating & Cooling to a prestigious renovation project to transform a Norther Italy 1700s Palace into comfortable offices
Posco Green building

Posco Green building

POSCO Green Building located on the Yonsei University International Campus in Songdo,  has been equipped with radiant underfloor heating and cooling and Comfort panels from Uponor.
National Library of Latvia

National Library of Latvia

National Library of Latvia is the most impressive industrial project in Latvia of the last decade. Uponor provided the building with Uponor underfloor heating and MLCP pipes.
Agder fengsel in Norway

Agder fengsel in Norway

Statsbygg har fått i oppdrag av Justisdepartementet å bygge nytt fengsel i Agder, med avdelinger i Mandal og på Froland. Uponor fikk i oppdrag med å levere gulvvarme til begge fengslene, ca 100 000 meter med rør. Det er lagt gulvvarme i alle  rom på begge prosjektene. Uponor har også levert tappevann; Mandal fengsel med nye PPM fordelere, Froland fengsel messingfordelere. Uponor har også levert noe Ecoflex rør til prosjektene.
The New Deichmanske Library - Bjørvika, Oslo

The New Deichmanske Library - Bjørvika, Oslo

Deichman is equipped with Thermally Active Building System - a system for storing the energy in the concrete ceiling. It is primarily a cooling system, but it can also be used as a heating system. When in cooling mode, no energy is used as the heat is drawn into the concrete, only when it is transferred from the concrete and into the water pipes that are cast in the decking. The need for installed power is reduced, and operating expenses are significantly reduced as opposed to in a air-based cooling system. The TABS is cast into the Prefab elements, which is a BubbleDeck construction with spans up to 10.5 meters.
BAE Systems Rochester

BAE Systems Rochester

BAE systems are the third largest global defence company, delivering a range of products for the air, land and naval armed forces.
Rivergate

Rivergate

The RIVERGATE office building in Vienna, Austria, was certified as a Green Building by the EU andrelies on the efficient Contec ON concrete surface activation.
Berger Logistik

Berger Logistik

Berger Logistik transports goods by land, sea and air around the globe. The company was founded in 1961 by Johann Berger and is based in Wörgl, in the Tyrol region of Austria. 
Sunesis school scheme: Sacred Heart Primary School, West Midlands

Sunesis school scheme: Sacred Heart Primary School, West Midlands

Uponor were nominated as the sole supplier for radiant heating systems for the Sunesis Schools schemes, with Main Contractor Willmott Dixon. Sunesis is a Joint Venture between Scape and Willmott Dixon, built on the combined experience of public sector know-how and private expertise. They are the market leader in delivering pre-designed buildings across a range of market sectors. Every design has a defined layout, specification, fixed cost and timescale to construct. The full benefits of a full BIM model are also utilised.

New office in Västerås with a focus on modern and environmentally friendly solutions

New office in Västerås with a focus on modern and environmentally friendly solutions

The plumbing company Mälardalens Rör in Västerås moved from their premises that they had been in since the end of the 80s. In November 2021, the first test trench was taken and at the turn of the year 2022/2023 they moved into the new office on a plot of land they have owned for a long time. We visited and spoke with the owners Robert Lind and Veronica Lange to hear more about the project.
HAMK's zero-energy hall uses energy piles

HAMK's zero-energy hall uses energy piles

Construction of Finland's first virtually zero-energy hall was completed in May 2015. The hall was built for the Thin Sheet Centre research unit of the Häme University of Applied Sciences (HAMK) and it draws its energy primarily from energy piles and solar panels.
Institut les Mines Telecoms Saclay

Institut les Mines Telecoms Saclay

Le bâtiment d’enseignement supérieur et de recherche pour l’Institut Mines-Télécom intègre un système de dalle active sur une surface de 40 000 m2. Le bâtiment économe en énergie accueillera une gamme variée d’activités propres à l’Institut Mines - Télécom : formations, recherches, transfert et innovation.

Villeroy & Boch

Villeroy & Boch

Part of the historic abbey complex on the premises of Villeroy & Boch's headquarters in Mettlach has been completely renovated.
Poslovni centar Adris grupe

Poslovni centar Adris grupe

Arhitektonski projekt poslovnog centra Adris u Jagićevoj ulici 33. u Zagrebu, spoj je klasičnog i modernog. Gradnja poslovnog centra započeta je 2011., a završena 2015. kada se u nju smještaju zaposlenici Adris grupe i Croatia osiguranja. 
City Hall

City Hall

The challenge began in 2021 when the building was completely redesigned to cut energy waste. Uponor Ecomate was installed to gain actionable insights into heating, cooling and power usage and improve the Town Hall's energy consumption and carbon footprint.
Magnum Business center

Magnum Business center

MAGNUM – a brand new business centre. One of the largest in Kaunas city in Lithuania.

MAGNUM aims to introduce positive change, an innovative work culture, and a responsible attitude to the environment. It will inspire these aims not only in its residents, but in the city of Kaunas itself — a city that is rapidly growing and changing.

Edificio de oficias en calle Tutor

Edificio de oficias en calle Tutor

The building located at Calle Tutor 16 (Madrid), owned by Arquia Inmuebles, has undergone a complete renovation and modernization, being partially demolished with the façade stabilized. A project designed by Tuñón y Albornoz Arquitectos and executed by SANJOSE Constructora, where the integration of Uponor's Invisible Air Conditioning in the Matrics raised technical floor developed by company Subway Systems.
Ilmalanlinna, Helsinki

Ilmalanlinna, Helsinki

Due to the interest rates of the floor structures, underfloor heating at Uponor's new head office required a solution that would raise the floor surface as little as possible. A functional result was achieved with an unusual implementation, low-structure underfloor heating plates, which are mainly used in renovations of detached houses, and which increase the floor height by only 15 millimetres.