Construction of raw water pipelines for the power plant

Construction of raw water pipelines for the power plant

One of Europe’s largest power plants is being built in Kozienice in central Poland. Uponor Infra pipes and manholes were used when building the raw water line.
Reference report as PDF

One of Europe’s largest power plants is being built in Kozienice in central Poland. Uponor Infra pipes and manholes were used when building the raw water line. Uponor Infra also provided technical support, as well as welding and assembly work.

Project Information

Country
Poland

Website

Completion
2016

Project Type
New Build

Size
Weholite pipes DN1000 SN8 (ca. 70m) and manholes DN1800, pressure pipes: PE100 PN7.5 SDR22 d.800x36.4mm – 405m and PE100 PN10 SDR17 d.800x47.4mm – 236m

Partners

Investor:
ENEA SA
Head designer:
ENERGOPROJEKT - WARSZAWA SA
Contractor:
Consortium of Mitsubishi Hitachi Power Systems Europe GmbH (MHPSE) and Polimex-Mostostal S.A

 