UPONOR, s.r.o.
Vajnorská 105, 831 04 Bratislava
Prípadová štúdia

The installation of Uponor storm water cassettes in Shopping Center Karisma, Lahti, Lahti, Finland

The installation of Uponor storm water cassettes in Shopping Center Karisma, Lahti

Fakty o projekte

Lahti, Finland
Kancelárské budovy
Búrková voda
Dokončenie: 2011

Uponor participácia

0
Karisma has about 33500 m2 of sales area and nearly 80 stores in two floors. Approximately 3 million customer visits per year is expected. Large number of visitors also requires a large parking place which can be found in Karisma. The parking place is able to hold about 1,600 cars.

Storm water under control with Uponor storm water cassettes

Shopping centre and its parking place forms together the area of 7.5 acres which rain and melt water management requires a robust system. Directing large water masses directly to the city´s storm drain would cause serious capacity problems. Also directing water into the terrain was out of the question. Uponor storm water cassettes were found to be the solution. Water from the roof of the building and from the asphalted parking lot is directed to the cassette field. Uponor storm water cassettes are usually used directly to infiltrate storm water into the soil. In this project that was not possible because of the level of groundwater was too high.

There are two cassette areas in Karisma and one of them includes a sand pit. Cassette areas are 130 m3 and 370 m3 in size. Approximately 1700 Uponor storm water cassettes were needed in the site.

“The delay systems are virtually solid containers in which the cassette areas are surrounded with welded polyethylene film. “ Says Project Manager Esa-Matti Laurell From SRV. The amount of storm water is huge. A good example of that is the size of the storm water pipes which comes in to the cassette field. Their diameter is 670mm.  The outgoing pipes which lead the water from the cassette field into the Kymijärvi Lake are much smaller. Their diameter is only 315mm. This ensures that the sewer capacity is adequate also during heavy rain. Water from the smaller cassette field is directed into the ditch and finally into the forest wetland.

Smaller cassette area is located into the traffic area so the load resistance was also paid attention to.  The cassettes are installed about 1.5 meters deep and no problems have occurred. So according to this experience, Uponor storm water cassettes can also be installed in traffic areas.

Good feedback from builders

Heinolan Maansiirto Lp was responsible for Karisma Construction. Installation of the Uponor Storm water cassettes and the welding of the surrounding film were handled by subcontractor Kiinteistö Sokka Ltd. “This project was a substantial two-year-job for us. “ Says Jorma Saarinen from Heinolan Maansiirto Lp. “We did all the groundwork with sewers all the way to the asphalt. We have not installed cassette systems before, but with this experience it seems to be a successful solution. Compared to conventional systems the capacity of the Uponor storm water cassettes is much better”

Mika Peltola from Kiinteistö Sokka Ltd was responsible for stacking the cassettes and welding the film. He agrees with Mr. Saarinen: “The product is great and it is also quick and easy to install. I personally have been involved in several cassette installation projects, so I have previous experience of this kind of systems. “

The installation of Uponor storm water cassettes in Shopping Center Karisma, Lahti

0002950

Projektové informácie

Projektové informácie

Krajina
Finland
Dokončenie
2011
Typ projektu
Novostavba
Typ budovy
Kancelárské budovy

Partneri

Partneri

developer
Kesko Oyj
Konsernin viestintä ja yhteiskuntavastuu Satamakatu 3, Helsinki 00016 Kesko Puhelinvaihde, puh. 010 5311
Finland

contractor
SRV Rakennus oy
PL 500, 02201 Espoo Puhelinvaihde: 020 145 5200
Finland

installer
Heinolan Maansiirto Ky
Sarvikatu 3 18100 Heinola Puh: 0500 - 491 093
Finland

Podobné projekty

Bayer Qingdao ECB Lighthouse

Bayer Qingdao ECB Lighthouse

ECB Lighthouse, which serves as the administration building of a Bayer MaterialScience plant in Qingdao, is the first building in China of the Bayer Eco Commercial Building (ECB) Program.
Day-care centre to be built with energy piles

Day-care centre to be built with energy piles

As requested by the City of Vantaa, the Vaaralanpuisto day-care centre has been planned based on the "nearly 0 energy days" concept. Construction work for the day-care centre began in late summer 2016, and the project will be completed in July 2017. Project costs are estimated at EUR 5.4 million, and the day-care centre will accommodate about 130 children. Among the various energy production options available for the site, the City of Vantaa chose the energy pile and solar thermal collector system jointly developed by Uponor and Ruukki.
Auron

Auron

The Uponor Contec ON concrete surface activation heats and cools the AURON office building complex in Munich.
Energy Efficiency Center

Energy Efficiency Center

The foyer, information centre and conference room at the Energy Efficiency Centre in Würzburg uses the Uponor Klett line for energy-efficient radiant heating and cooling.
Ericusspitze Spiegelhaus

Ericusspitze Spiegelhaus

New company HQ of the Spiegel Group is located at the Ericusspitze. The concrete core activation from Uponor ensures pleasant temperature levels in the building.
Brain Box Berlin

Brain Box Berlin

Thermal concrete core activation with Uponor Contec provides economical, energy-efficient and sustainable building temperature control in the new landmark Adlershof Science and Technology Centre.

 

Leitradlofts, Cologne

Leitradlofts, Cologne

A hygienically optimal drinking water installation was integrated into the new office complex – thanks to Uni Pipe PLUS within a very short time.

First Uponor Comfort Panel project in Hungary

First Uponor Comfort Panel project in Hungary

An office building, where proper comfort is provided for doing your job The commercial buildings provide more or less limited space as the workplace for people. Therefore cooling the air is an important factor in maintaining their comfort during their stay. In order to keep the daily work undisturbed, the system used should be installed easily, should be efficient economically, and should be hygienic.
Immeuble Delta Green

Immeuble Delta Green

La dalle active Uponor est intégrée depuis 2017 dans l’immeuble Delta Green, bâtiment tertiaire de 4600m2 comprenant 4 niveaux. Celui-ci est le premier bâtiment de la région tout à fait autonome en énergie.

Standard Bank

Standard Bank

Uponor PE-Xa pipe used for refurbishment of chilled water pipelines in the head office of South Africa's Standard Bank located in Johannesburg.
Palazzo Ferrazzi - Brescia

Palazzo Ferrazzi - Brescia

Uponor brings the comfort of its Underfloor Heating & Cooling to a prestigious renovation project to transform a Norther Italy 1700s Palace into comfortable offices
Posco Green building

Posco Green building

POSCO Green Building located on the Yonsei University International Campus in Songdo,  has been equipped with radiant underfloor heating and cooling and Comfort panels from Uponor.
National Library of Latvia

National Library of Latvia

National Library of Latvia is the most impressive industrial project in Latvia of the last decade. Uponor provided the building with Uponor underfloor heating and MLCP pipes.
Agder fengsel in Norway

Agder fengsel in Norway

Statsbygg har fått i oppdrag av Justisdepartementet å bygge nytt fengsel i Agder, med avdelinger i Mandal og på Froland. Uponor fikk i oppdrag med å levere gulvvarme til begge fengslene, ca 100 000 meter med rør. Det er lagt gulvvarme i alle  rom på begge prosjektene. Uponor har også levert tappevann; Mandal fengsel med nye PPM fordelere, Froland fengsel messingfordelere. Uponor har også levert noe Ecoflex rør til prosjektene.
The New Deichmanske Library - Bjørvika, Oslo

The New Deichmanske Library - Bjørvika, Oslo

Deichman is equipped with Thermally Active Building System - a system for storing the energy in the concrete ceiling. It is primarily a cooling system, but it can also be used as a heating system. When in cooling mode, no energy is used as the heat is drawn into the concrete, only when it is transferred from the concrete and into the water pipes that are cast in the decking. The need for installed power is reduced, and operating expenses are significantly reduced as opposed to in a air-based cooling system. The TABS is cast into the Prefab elements, which is a BubbleDeck construction with spans up to 10.5 meters.
Rivergate

Rivergate

The RIVERGATE office building in Vienna, Austria, was certified as a Green Building by the EU andrelies on the efficient Contec ON concrete surface activation.
Berger Logistik

Berger Logistik

Berger Logistik transports goods by land, sea and air around the globe. The company was founded in 1961 by Johann Berger and is based in Wörgl, in the Tyrol region of Austria. 
Sunesis school scheme: Sacred Heart Primary School, West Midlands

Sunesis school scheme: Sacred Heart Primary School, West Midlands

Uponor were nominated as the sole supplier for radiant heating systems for the Sunesis Schools schemes, with Main Contractor Willmott Dixon. Sunesis is a Joint Venture between Scape and Willmott Dixon, built on the combined experience of public sector know-how and private expertise. They are the market leader in delivering pre-designed buildings across a range of market sectors. Every design has a defined layout, specification, fixed cost and timescale to construct. The full benefits of a full BIM model are also utilised.

HAMK's zero-energy hall uses energy piles

HAMK's zero-energy hall uses energy piles

Construction of Finland's first virtually zero-energy hall was completed in May 2015. The hall was built for the Thin Sheet Centre research unit of the Häme University of Applied Sciences (HAMK) and it draws its energy primarily from energy piles and solar panels.
Institut les Mines Telecoms Saclay

Institut les Mines Telecoms Saclay

Le bâtiment d’enseignement supérieur et de recherche pour l’Institut Mines-Télécom intègre un système de dalle active sur une surface de 40 000 m2. Le bâtiment économe en énergie accueillera une gamme variée d’activités propres à l’Institut Mines - Télécom : formations, recherches, transfert et innovation.

Villeroy & Boch

Villeroy & Boch

Part of the historic abbey complex on the premises of Villeroy & Boch's headquarters in Mettlach has been completely renovated.
Poslovni centar Adris grupe

Poslovni centar Adris grupe

Arhitektonski projekt poslovnog centra Adris u Jagićevoj ulici 33. u Zagrebu, spoj je klasičnog i modernog. Gradnja poslovnog centra započeta je 2011., a završena 2015. kada se u nju smještaju zaposlenici Adris grupe i Croatia osiguranja. 
City Hall

City Hall

The challenge began in 2021 when the building was completely redesigned to cut energy waste. Uponor Ecomate was installed to gain actionable insights into heating, cooling and power usage and improve the Town Hall's energy consumption and carbon footprint.
Magnum Business center

Magnum Business center

MAGNUM – a brand new business centre. One of the largest in Kaunas city in Lithuania.

MAGNUM aims to introduce positive change, an innovative work culture, and a responsible attitude to the environment. It will inspire these aims not only in its residents, but in the city of Kaunas itself — a city that is rapidly growing and changing.

Edificio de oficias en calle Tutor

Edificio de oficias en calle Tutor

The building located at Calle Tutor 16 (Madrid), owned by Arquia Inmuebles, has undergone a complete renovation and modernization, being partially demolished with the façade stabilized. A project designed by Tuñón y Albornoz Arquitectos and executed by SANJOSE Constructora, where the integration of Uponor's Invisible Air Conditioning in the Matrics raised technical floor developed by company Subway Systems.
Ilmalanlinna, Helsinki

Ilmalanlinna, Helsinki

Due to the interest rates of the floor structures, underfloor heating at Uponor's new head office required a solution that would raise the floor surface as little as possible. A functional result was achieved with an unusual implementation, low-structure underfloor heating plates, which are mainly used in renovations of detached houses, and which increase the floor height by only 15 millimetres.