Iisalmen Vesi renovated a trunk line by relining, Iisalmi, Finland
Iisalmen Vesi renovated a trunk line by relining
To rebuild an office building located in the heart of Amsterdam into 150 appartments in a relatively short time is definitely a big challenge.
Project facts
Uponor Involvement
"We don't even have the parts for repairing the asbestos-concrete pipe anymore," states Iisalmen Vesi's network engineer Seppo Keskinen.
Due to the presence of asbestos, special measures are also required when working on the pipe and processing waste material.
The motivation to renew the pipe grew stronger when Ylä-Savon Vesi Oy, a wholesale water company jointly owned by five municipalities, renovated the waterworks in Kyllikinranta, from where the trunk line in question runs towards the centre of Iisalmi.
When we started to think about how to rinse and disinfect the lines, the risks related to the pipe became apparent once again. We decided to renovate it," says Iisalmen Vesi's director Ulla Tyrväinen.
Easily under the railway
Relining emerged as the best option in the early stages, even though the line runs through a soft sandy area."More buildings have been built in the area after the original installation, and there are also long underpasses along the way. We decided that relining would be the most convenient way to renovate," says Tyrväinen.
The line also goes under the railway.
"By choosing relining, we avoided complex arrangements and permit applications," states Seppo Keskinen.
A permit was required only for a couple of relining excavations that extended near the railway.
Iisalmen Vesi chose Uponor Infra as the main contractor for relining and opted to use Profuse pipes.
"The Profuse pipe is most often the best choice for relining as the pipe's polypropylene layer protects the pipe during installation," states foreman Veli-Matti Hakala from Uponor Infra.
Without compromising on performance
Work began at the end of October with the cleaning of the old pipe. According to Hakala, the cast iron pipe usually has to be tinkered in order for the new pipe to fit inside. Instead, the inner surface of the asbestos-concrete pipe only collects slime, which can be removed by washing.The pipes were washed by pigging by Tampere-based SPC Vesitekniikka Oy. Foam plastic cylinders known as "pigs" were hydraulically pushed into the pipe at the waterworks end and out of it at the other end, cleaning the old pipe along the way.
"The entire line was cleaned in one time," says Hakala.
The 280-millimetre Profuse pipe was fitted smoothly into the 300-millimetre asbestos-concrete pipe. Therefore, there was no need to compromise on performance.
"It was interesting and surprising to see how small the clearances for relining were. There really wasn't much room," says Keskinen.
Over one thousand cubic metres of water, accounting for about one-fifth of the town's overall water consumption, flow through the line every day. There are about 22,000 inhabitants in Iisalmi.
Front end in use within a couple of weeks
The relining job was split into 150–200 m portions based on the line's valves and branches. Paltamo-based Pyykkönen Yhtiöt Oy dug a total of 14 excavations at both ends of the relinings, and the new pipe was winched inside the old one by a lorry. Uponor Infra's fitters built the lines from 12-metre pipes by percussion welding.Relining began at the town end immediately after washing, and the line was taken into use gradually as work progressed. Water was already flowing through the front end within a couple of weeks. Only one property needed a temporary surface water pipe.
"We kept water running every day to prevent it from freezing despite sub-zero temperatures," says Keskinen.
According to him, the pressure gauges froze during the pressure tests and the line valves had to be heated with vapour.
Seamless cooperation
In addition to the contractors, Iisalmen Vesi's fitters and network engineer Keskinen also participated in the project. They were responsible for opening and closing the valves. Hakala praises the cooperation for its smoothness and flexibility, thanks to which small changes could be made while work was in progress."Cooperation went very well, and Uponor Infra's foreman was extremely competent," adds Keskinen.
He states that the smoothness of work also resulted in cost savings. Uponor Infra charged based on actual costs. Therefore, Iisalmen Vesi ended up paying less than what they had budgeted.
"The work was completed well within schedule despite the arrival of harsh winter conditions towards its end," says Tyrväinen.
The project was completed at the turn of the year, and the finishing touches are scheduled for the coming spring.
– Uponor tidied the excavations up after spring thawing.
Project information
Project information
Partners
Main contractor: Uponor Infra Ltd
Pipe washing: SPC Vesitekniikka Oy
Public works contracting: Pyykkönen Yhtiöt Oy
Similar projects
Pump structure secures stormwater system’s long life
Drinking water passing through contaminated area in Thisted
Intake pipeline for seawater in Copenhagen Harbour
Butt welding by night of 900 mm pipes ensures stable operation of a district cooling solution in Copenhagen Harbour.
TV-Tower, Estonia
PE pressure sewer system from Harjavalta to the city of Pori
New Uponor IQ –Storm water system - Sustainability and Quality in Road Infrastructure
Ultra Double replace concrete pipe line in Raahe
ProFuse pressure pipe line provides drinking water to cottage owners in islands near by Uusikaupunki
Environmental friendly heating and storm water systems in new Launonen day-care centre
New water pipeline
Now that’s truly FAST
Secure tunnel trunk lines
Life is grand for graylings in the pure waters of Ounasjoki River
Europe’s largest ever plastic culvert goes to Norway
Don’t count on luck to protect you from flooding
Clean drinking water for 17,000 scouts
Weholite limits overflows and pollution in London
Handling storm water in a smart way
Urban runoff under control – quickly and easily
Relining to the rescue in Kajaani
Fighting against an ecological disaster in a world-record time
Rapid action was critical when a sewage collector broke in Warsaw, Poland, causing a massive waste spill into the Vistula River. Uponor Infra’s crew worked 24 hours a day in order to stop the pollution of the river. A temporary pipeline was produced, delivered and connected in just eight days.
Sewage pipelines to sewage treatment plant - HDD method
Collectors for sewage treatment plant
Renovation of reinforced concrete sewer - relining method
Sewage retention chanel
Renovation of cast iron water supply pipeline - swagelining
Thanks to swagelining technology, it was possible to carry out most of the water line modernisation works in the centre of the city of Łódź, in a built-up area, along traffic lanes with heavy traffic of motor vehicles and trams.
Sea outlet - discharge of stream water into the Gdańsk Bay part 2
Renovation of damaged stoneware collector – cracking/short relining
Sewage separation system
Construction of storm water collectors in Nowe Polkowice is one of the stages of a big investment concerning the drainage of the district.
Sea outlet of treated wastewater
A sea outlet of treated wastewater was initiated in Swarzewo. It is yet another of the many environmentally friendly projects that have recently been carried out in Poland where PE pipes were used.
Uponor pressure pipe system Profuse in Borås town
Uponor Infra culverts in major investment at Skåne University Hospital in Malmö
A test installation of an infra culvert with great potential
Strong, Safe and Flexible
Innovative, reliable - and installed in 11 days
Uponor soil drainage system Ultra Rib 2 in Kungälv
Infratunnel protects pipes and cables in new residential area
Focus on sustainability
Weholite installed in Valdemarsvik Sweden
Uponor Vault cleans the storm water
Hybrid solutions for storm water management
City of Lahti is building new neighborhood called Ranta-Kartano. While they were constructing basic infrastucture the city saw the possibilty to reserve some ground space for storm water management. Now there is a test running for different kind of storm water management. Uponor is involved with new type of storm water filter.
An easy and reliable storm water solution
Flow measurement reveals leaks in the water supply network
Fire wastewater safely recovered
Water treatment plant
A smart retention system for an anti-flooding solution
September 2018 saw the launch of the project for a stormwater drainage system in Rzeszów, almost 26 kilometres long, in the residential District of Budziwój, which partially coincides with the floodplain of the River Wisłok. One of the elements of this system is the retention canal. The project, scheduled for delivery by May 2020, will help to finally solve flooding problems which have been plaguing the residents of this region of Poland.