Project facts
Uponor Involvement
installation of Uponor Ultra Double with it’s biggest diameter 680 mm
Uponor Ultra Double is a sewer system which is easy and fast to install. The size variety is wide from 200 mm up to 680 mm including also the fittings. The Ultra Rib 2 fitting system is suitable also for Ultra Double system as well many other Uponor’s pipe system. Ultra Double pipe has a solid socket and together with the durable sealing ring, the joint is always tight. In addition, the solid socket reduces 50% the amount of joints in pipeline. Therefore the maintenance cost later on are low. Uponor Ultra Double system has the Nordic Polymark approval.
New pipe line to replace the old concrete pipe line
The first installation for Uponor Ultra Double was made with it’s biggest diameter 680 mm. The target was at the centre of Raahe city where old leaking sewer pipe line was replaced by Ultra Double. According to the CEO of Raahe Vesi, Mr. Esa Seppänen, the old concrete pipes were still on quite good condition but the joints were leaking in and the amount of sewer water was increased. Naturally, the costs of purification of sewer water were high.
The new sewer is the same diameter than the old pipe line, 680 mm. But the flow circumstances are clearly better so the overall capacity will be enough. Despite that in couple of years there will be even 6 new multistory buildings in the centre which will be connected to the sewer pipe line, says Esa Seppänen. The most important factor in decision making was the joint technique that Uponor Ultra Double has. The tight joints are key issues in Raahe due to that the pipe line is installed lower than sea level. The danger of ground water leaking inside the pipe line is high as the old concrete joints proved. With Uponor Ultra Double there are significantly less joints in pipe line and together with durable sealing ring the leaking problem is now over.
The new pipe line is about 260 m long. While the old concrete pipes were excavated the new pipes were installed which made the whole process easy and fast. The excavation work was made by Maanrakennus E. Majava Oy and the pipes were installed by Raahen Vesi Oy’s own installers.
Project information
Project information
Partners
contractor
Maanrakennus E. Majava Oy
installer
Raahen Vesi Oy
Similar projects
Pump structure secures stormwater system’s long life
Drinking water passing through contaminated area in Thisted
Intake pipeline for seawater in Copenhagen Harbour
Butt welding by night of 900 mm pipes ensures stable operation of a district cooling solution in Copenhagen Harbour.
TV-Tower, Estonia
PE pressure sewer system from Harjavalta to the city of Pori
New Uponor IQ –Storm water system - Sustainability and Quality in Road Infrastructure
ProFuse pressure pipe line provides drinking water to cottage owners in islands near by Uusikaupunki
Environmental friendly heating and storm water systems in new Launonen day-care centre
New water pipeline
Now that’s truly FAST
Handling storm water in a smart way
Secure tunnel trunk lines
Life is grand for graylings in the pure waters of Ounasjoki River
Europe’s largest ever plastic culvert goes to Norway
Don’t count on luck to protect you from flooding
Clean drinking water for 17,000 scouts
Iisalmen Vesi renovated a trunk line by relining
To rebuild an office building located in the heart of Amsterdam into 150 appartments in a relatively short time is definitely a big challenge.
Weholite limits overflows and pollution in London
Weholite installed in Valdemarsvik Sweden
Uponor Vault cleans the storm water
Fighting against an ecological disaster in a world-record time
Rapid action was critical when a sewage collector broke in Warsaw, Poland, causing a massive waste spill into the Vistula River. Uponor Infra’s crew worked 24 hours a day in order to stop the pollution of the river. A temporary pipeline was produced, delivered and connected in just eight days.
Sewage pipelines to sewage treatment plant - HDD method
Collectors for sewage treatment plant
Renovation of reinforced concrete sewer - relining method
Sewage retention chanel
Renovation of cast iron water supply pipeline - swagelining
Thanks to swagelining technology, it was possible to carry out most of the water line modernisation works in the centre of the city of Łódź, in a built-up area, along traffic lanes with heavy traffic of motor vehicles and trams.
Sea outlet - discharge of stream water into the Gdańsk Bay part 2
Renovation of damaged stoneware collector – cracking/short relining
Sewage separation system
Construction of storm water collectors in Nowe Polkowice is one of the stages of a big investment concerning the drainage of the district.
Sea outlet of treated wastewater
A sea outlet of treated wastewater was initiated in Swarzewo. It is yet another of the many environmentally friendly projects that have recently been carried out in Poland where PE pipes were used.
Uponor pressure pipe system Profuse in Borås town
Uponor Infra culverts in major investment at Skåne University Hospital in Malmö
A test installation of an infra culvert with great potential
Strong, Safe and Flexible
Innovative, reliable - and installed in 11 days
Uponor soil drainage system Ultra Rib 2 in Kungälv
Infratunnel protects pipes and cables in new residential area
Focus on sustainability
Hybrid solutions for storm water management
City of Lahti is building new neighborhood called Ranta-Kartano. While they were constructing basic infrastucture the city saw the possibilty to reserve some ground space for storm water management. Now there is a test running for different kind of storm water management. Uponor is involved with new type of storm water filter.
An easy and reliable storm water solution
Flow measurement reveals leaks in the water supply network
Fire wastewater safely recovered
Water treatment plant
Quick installation in the Konotopa channel
Super-sized cooling
Weholite tanks have multiple uses
Water supply in very demanding terrain in Norway
A smart retention system for an anti-flooding solution
September 2018 saw the launch of the project for a stormwater drainage system in Rzeszów, almost 26 kilometres long, in the residential District of Budziwój, which partially coincides with the floodplain of the River Wisłok. One of the elements of this system is the retention canal. The project, scheduled for delivery by May 2020, will help to finally solve flooding problems which have been plaguing the residents of this region of Poland.