HAMK's zero-energy hall uses energy piles, Hämeenlinna, Finland

HAMK's zero-energy hall uses energy piles

Construction of Finland's first virtually zero-energy hall was completed in May 2015. The hall was built to provide new premises for the Thin Sheet Centre research unit of the Häme University of Applied Sciences (HAMK). It is also used for research, development and teaching activities. The hall draws its energy primarily from energy piles and solar panels.

Коротко про проєкт

Hämeenlinna, Finland
Офісні будівлі
Геотермальні системи
Рік завершення будівництва: 2015

Вклад Uponor

2.8km of collection pipes and 60 energy piles
The approach was to create a building that exploits renewable energy as efficiently as possible.

"We have long been developing concepts for constructing halls for commercial and industrial uses, as well as concepts related to virtually zero-energy buildings. We have collaborated extensively with HAMK in Hämeenlinna and when the Thin Sheet Centre needed new premises, it was considered to be a good opportunity to pilot zero-energy construction," says Jyrki Kesti, Technology Director from Ruukki.

 

The ideal site for energy piles

The construction project combined several different energy efficiency measures, making it an excellent fit for the energy pile system that was jointly developed by Uponor and Ruukki. The piles are supplemented by the solar energy that is collected by the building.

In the winter, the energy piles, which are used in the foundations, transfer energy from the ground for use in heating the building. In the summer, they transfer heat energy, which is produced by the solar energy collectors installed on the roof and by the cooling system, back into the ground, enabling the stored heat to be re-used for heating the building in the winter. The energy level of the ground thereby remains suitable for energy generation.

 

Installation was completed without any problems

Uponor installed a total of 2.8 kilometres of heat collection piping into sixty energy piles on the site in summer 2014.

"The installation went well. Our part of the project began after piling when we received a log of the piling work. This showed the lengths of the piles, enabling us to manufacture collectors," says Tuomas Eskelinen, Uponor's project coordinator.

"We installed the collectors on-site within a week of receiving the log. The next stage of the on-site project is to cast sensors. After that, we will return to connect transfer pipes from the piles to the manifolds. At the end, we will pressurise the system for testing," says Eskelinen.

 

It is worth being energy efficient

Implementing the hall in the form of a virtually zero-energy solution was approximately EUR 70,000 more expensive than building a conventional hall but, according to the calculations, the energy investments will pay for themselves within just over ten years. After this, the maintenance and usage costs of the hall will be easy on the wallet.

Energy piles and other solutions that exploit renewable energy provide numerous advantages to property owners.

"The energy bill can be halved and the investments have a very reasonable break-even period. The resale value also remains good as the technical solutions in question are durable," says Jyrki Kesti.

 

A solution for better construction

The hall was designed as a single entity from the start.

"On a Finnish scale, the site was unique. It is the only hall that can operate with such low consumption. It was of essential importance to view the hall as a single entity during the design phase as the hall includes a large number of different energy efficiency solutions in one package," says Kesti.

"Construction regulations do not yet stipulate energy efficiency of this order but we wanted to demonstrate that it is possible and cost effective even today. According to our calculations, a better building solution of this type also makes financial sense."

HAMK's zero-energy hall uses energy piles

hamk_1

Інформація про проєкт

Інформація про проєкт

Адреса
Visakaarre 9, 13100 Hämeenlinna, Finland
Країна
Finland
Рік завершення будівництва
2015
Тип проєкту
Референс об'єкти
Тип будівлі
Офісні будівлі

Партнери

Партнери
Ruukki Construction

Подібні проєкти

Бізнес центр в Києві

Бізнес центр в Києві

Будівництво нового восьмиповерхового бізнес-центру на М.Вовчка 18а розпочато в 2016 році з метою збільшення площ для здійснення підприємницької діяльності. Будівля має зручне розташування та місцезнаходження та є складовою частиною комплекса, що включає в собі складські площі, логістичний вузол та офісні приміщення.
Day-care centre to be built with energy piles

Day-care centre to be built with energy piles

As requested by the City of Vantaa, the Vaaralanpuisto day-care centre has been planned based on the "nearly 0 energy days" concept. Construction work for the day-care centre began in late summer 2016, and the project will be completed in July 2017. Project costs are estimated at EUR 5.4 million, and the day-care centre will accommodate about 130 children. Among the various energy production options available for the site, the City of Vantaa chose the energy pile and solar thermal collector system jointly developed by Uponor and Ruukki.
First Uponor Comfort Panel project in Hungary

First Uponor Comfort Panel project in Hungary

An office building, where proper comfort is provided for doing your job The commercial buildings provide more or less limited space as the workplace for people. Therefore cooling the air is an important factor in maintaining their comfort during their stay. In order to keep the daily work undisturbed, the system used should be installed easily, should be efficient economically, and should be hygienic.
Agder fengsel in Norway

Agder fengsel in Norway

Statsbygg har fått i oppdrag av Justisdepartementet å bygge nytt fengsel i Agder, med avdelinger i Mandal og på Froland. Uponor fikk i oppdrag med å levere gulvvarme til begge fengslene, ca 100 000 meter med rør. Det er lagt gulvvarme i alle  rom på begge prosjektene. Uponor har også levert tappevann; Mandal fengsel med nye PPM fordelere, Froland fengsel messingfordelere. Uponor har også levert noe Ecoflex rør til prosjektene.
The New Deichmanske Library - Bjørvika, Oslo

The New Deichmanske Library - Bjørvika, Oslo

Deichman is equipped with Thermally Active Building System - a system for storing the energy in the concrete ceiling. It is primarily a cooling system, but it can also be used as a heating system. When in cooling mode, no energy is used as the heat is drawn into the concrete, only when it is transferred from the concrete and into the water pipes that are cast in the decking. The need for installed power is reduced, and operating expenses are significantly reduced as opposed to in a air-based cooling system. The TABS is cast into the Prefab elements, which is a BubbleDeck construction with spans up to 10.5 meters.
Sunesis school scheme: Sacred Heart Primary School, West Midlands

Sunesis school scheme: Sacred Heart Primary School, West Midlands

Uponor were nominated as the sole supplier for radiant heating systems for the Sunesis Schools schemes, with Main Contractor Willmott Dixon. Sunesis is a Joint Venture between Scape and Willmott Dixon, built on the combined experience of public sector know-how and private expertise. They are the market leader in delivering pre-designed buildings across a range of market sectors. Every design has a defined layout, specification, fixed cost and timescale to construct. The full benefits of a full BIM model are also utilised.

New office in Västerås with a focus on modern and environmentally friendly solutions

New office in Västerås with a focus on modern and environmentally friendly solutions

The plumbing company Mälardalens Rör in Västerås moved from their premises that they had been in since the end of the 80s. In November 2021, the first test trench was taken and at the turn of the year 2022/2023 they moved into the new office on a plot of land they have owned for a long time. We visited and spoke with the owners Robert Lind and Veronica Lange to hear more about the project.
Institut les Mines Telecoms Saclay

Institut les Mines Telecoms Saclay

Le bâtiment d’enseignement supérieur et de recherche pour l’Institut Mines-Télécom intègre un système de dalle active sur une surface de 40 000 m2. Le bâtiment économe en énergie accueillera une gamme variée d’activités propres à l’Institut Mines - Télécom : formations, recherches, transfert et innovation.

City Hall

City Hall

The challenge began in 2021 when the building was completely redesigned to cut energy waste. Uponor Ecomate was installed to gain actionable insights into heating, cooling and power usage and improve the Town Hall's energy consumption and carbon footprint.
Magnum Business center

Magnum Business center

MAGNUM – a brand new business centre. One of the largest in Kaunas city in Lithuania.

MAGNUM aims to introduce positive change, an innovative work culture, and a responsible attitude to the environment. It will inspire these aims not only in its residents, but in the city of Kaunas itself — a city that is rapidly growing and changing.

Edificio de oficias en calle Tutor

Edificio de oficias en calle Tutor

The building located at Calle Tutor 16 (Madrid), owned by Arquia Inmuebles, has undergone a complete renovation and modernization, being partially demolished with the façade stabilized. A project designed by Tuñón y Albornoz Arquitectos and executed by SANJOSE Constructora, where the integration of Uponor's Invisible Air Conditioning in the Matrics raised technical floor developed by company Subway Systems.
Ilmalanlinna, Helsinki

Ilmalanlinna, Helsinki

Due to the interest rates of the floor structures, underfloor heating at Uponor's new head office required a solution that would raise the floor surface as little as possible. A functional result was achieved with an unusual implementation, low-structure underfloor heating plates, which are mainly used in renovations of detached houses, and which increase the floor height by only 15 millimetres.