Търговско представителство
Uponor GmbH – България
Казус

New apartment building, Kirkkonummi, Finland

New block of flats built with Uponor's R2i elements

Two blocks of rental flats were completed at Sokeritehtaantie 15 in Kirkonummi in summer 2015. The new sites were realised with Uponor's R2i elements.

Факти за проекта:

Kirkkonummi, Finland
Многоетажна сграда
Индивидуални абонатни станции
Завършване: 2015
Managing Director Juha Marjamo from Kirkkonummen Vuokra-asunnot Oy says that ready to install (R2i) elements made it possible to put the wall between the bathroom and the hallway to effective use. Ease of maintenance is also fundamental as inspections and maintenance measures are easy to carry out thanks to the openable structure of the elements.

- The site was completed on schedule, and no maintenance work has been required since its completion. The solution works well, states a satisfied Juha Marjamo, Managing Director at Kirkkonummen Vuokra-asunnot Oy.

 

Benefits throughout the building's life cycle

R2i elements are manufactured under controlled factory conditions and are then taken to the site when they are needed there. This reduces the amount of work to be carried out at the construction site, thus accelerating construction. The use of elements offers advantages not only during construction but also during use and maintenance. Thanks to their openable casing, the water and heat pipes on Sokeritehtaantie are easy to inspect and fully replaceable. The underfloor heating control unit, valves and shut-off valves are in their own casing on the hallway side. Uponor also delivered a Comfort thermal floor equipped with regulators to Sokeritehtaantie.

- It was possible to connect the underfloor heating manifold cabinet integrated in the back side of the elements directly to the trunk line on the other side. This way, we avoided the typically troublesome pipe casings necessary in the presence of horizontal pulls, as well as other adverse effects of on-site construction on schedules and costs at the construction site, says Uponor's Project Development Manager Toni Wahlfors.
 
The main contractor was V O Mattila Oy. Uponor installed all R2i elements. The project was commissioned by Kirkkonummen Vuokra-asunnot Oy, and the piping contractor was Skanska Lahti.

- Uponor delivered the R2i elements in batches. All elements were installed within a short period of time, and everything went smoothly. In terms of maintenance, the Uponor service flue is an excellent choice. There have been no complaints as I'd be one of the first to hear about them, says Väinö Kananoja from V O Mattila Oy, the main contractor.

When pre-manufactured elements are used, the erection of the frame line does not affect processes or schedules at the construction site.

-    The project included all necessary pipes, connections, insulation and fire protection material for the entire line (in the elements and between floors). As the elements had pre-manufactured connections, the piping contractor could quickly move on to couple the fittings, states Toni Wahlfors from Uponor. 

New block of flats built with Uponor's R2i elements

sokeritehtaantie2_valmistuu_kuva_700x450

Информация за проекта

Информация за проекта

Държава
Finland
Завършване
2015
Тип на проекта
Нова сграда
Тип сграда
Многоетажна сграда

Партньори

Партньори

Planners: Helsingin Kartech Oy
Building owner: Kirkkonummen Vuokra-Asunnot Oy
Fitter: Skanska Talonrakennus Oy
Construction company: Rakennustoimisto V.O. Mattila Oy
 

Подобни проекти

Infinity Forest Residence

Infinity Forest Residence

Достъпно и сред природата, обектът е сред чист планински въздух, щедро слънце, обграден от богата, гориста и паркова растителност.
 В основата на философията за изграждането на Infinity Forest Residence стоят ключовите думи:
 практичност, ефективност, простор, свобода и здравословен живот.
 

 
Skyhouse

Skyhouse

Witness the premium customer experience during this hands-on support as this Austin Texas apartment complex converts...
Uponor participates in construction of Maarjamõisa Medical Campus

Uponor participates in construction of Maarjamõisa Medical Campus

2022 sees the completion of Maarjamõisa Medical Campus managed by Tartu University Hospital. The largest centre of its kind in Estonia, the Campus concentrates active medical care in one compact system. Uponor Estonia is participating as advisor, and as supplier of potable and heating water systems in the second construction phase currently under way.
Underfloor cooling adds value to new construction

Underfloor cooling adds value to new construction

Postitalo, the former post office building in downtown Tampere, got a new look in 2017 when it was renovated into new commercial premises and a block of flats was built on top. The heat distribution system of choice was Uponor's underfloor heating and cooling system, which was installed in all flats.
A housing company Petreliuksenrinne

A housing company Petreliuksenrinne

The Petreliuksenrinne housing company controls a group of residential buildings that were constructed in 1969. The company manages 124 flats, which were subject to an overhaul of their water supply and sewerage systems. The floor drains, bathrooms, electricity distribution and antenna systems were also overhauled.
Apartment building Varsta Oy

Apartment building Varsta Oy

Line renovations in blocks of flats can be conducted significantly faster and more easily. The Uponor R2I cassette makes for a problem-free renovation. Thanks to advanced prefabrication, the project period is shorter and the risks are lower. The As Oy Varsta company in Turku is the first R2I pilot site. The site will be completed to an expedited schedule.
Aleksanterinkatu 5 in Lahti will be completed with R2I blocks

Aleksanterinkatu 5 in Lahti will be completed with R2I blocks

An 8-storey apartment is rising in a former bank district in Lahti. The target will contain 265 apartments and is designed by A1 Arkkitehdit Oy and will be built by Nuorisosäätiö. There are 256 rental apartments reserved for students on floors 2-7. Uponor R2I blocks will be installed in all of the student-apartments in connection with bathroom and kitchen elements. Aleksi 5 is the first new destination in which R2I blocks are being delivered and in which sound-absorbing Decibel drains are used.
LEO 250

LEO 250

"LEO 250" brings together sophisticated architecture and superb energy efficiency. Construction time was speed up due to the use of an Uponor systems.
Grand Tower

Grand Tower

More than 400 heat interface units and over 300 km of underfloor heating and cooling pipes for Germany’s highest residential complex.
Ewha Campus Complex

Ewha Campus Complex

Ewha Womans University had planned the underground campus, which is a global trend for space creation, in order to solve the problem that the available space on the ground was insufficient despite the increase in the space demand in the campus, in accordance with the Ewha Womans University Development Plan in the 21st century.

George Street

George Street

Uponor products set the standard for off-site construction projects by providing a quick to install, cost-effective and high performance plumbing system for the safe delivery of domestic water services for the world’s tallest modular apartment building.
Sluseholmen

Sluseholmen

The Uponor project ’Sluseholmen’ has served as inspiration for developing a brand new and advantageous plumbing solution.
As a result, Uponor now offers a new, optimized and well structured, compact and easy to use prefab basic unit with flexible connectivity options for managing water and heating in varying types of housing.
From now on, Uponor provides the construction market with these prefab shaft units, primarily intended for modern floor building and terraced houses.
 
Brusaporto apartments

Brusaporto apartments

Two apartment buildings in Brusaporto, Italy, offer a high level of living comfort after renovation – also thanks to the Uponor Minitec underfloor heating system. With its low installation height, it is ideally suited for retrofitting.
Applewood Pointe

Applewood Pointe

Developed by Uponor, this new solution takes the guesswork and freelancing out of piping installations. Each kit, which includes all the needed ProPEX® fittings, adapters, valves, and rings, is delivered to the job site — one kit per room or apartment — along with a material list and an isometric layout for the installer to follow, helping to minimize mistakes and maximize efficiency.
Refurbishment of a prefabricated building

Refurbishment of a prefabricated building

During the renovation of a prefabricated building in Zwickau, Robinienweg, a low installation height stood in contrast to the desire for more energy efficiency and comfort through underfloor heating. The solution: a slimline combination of Minitec underfloor heating from Uponor and N 440 leveling screed from Knauf.