Sewage pipelines to sewage treatment plant - HDD method, Szczecin, Poland
Building of forced sewage pipelines to sewage treatment plant - HDD method
In 2007 in Szczecin, a series of record-breaking in the European scale number of crossings of a high dimension PEHD pipeline under a water obstacle made with a horizontal drilling method was completed in Szczecin. The engineering work was done within the "Improving water quality in Szczecin" programme.
Projektin tiedot
Uponorin osallistuminen
The contractor scheduled using 3 different pipeline founding technologies: open excavation, microtunneling and horizontal drilling, where 6 largest crossings under water obstacles with the total length of over 3 km was done without excavation. The open excavation and microtunneling technology used standard PEHD WehoPipe pipes with DN 1000 x 59.3 mm PN 10 SDR 17. In the tunnels made by horizontal drilling, due to very hard geological conditions and founding at the depth of ca. 20 m, pipes with thicker outer walls were applied (dzxe 1033.2 x 75.9 SDR 13.6 MOP 12.5). The pipes were produced and delivered to the site in 15-metre sections to minimise the number of welds on the pipeline course.
In December 2006 after making pilot drilling, the first actual drill was made at the Customs Office. 460 and 465 m long sections were pulled into the drill under the Oder. The pipeline sections under the Parnicki Canal - 360 and 570 m long were founded in February 2007. With regard to a lack of space to mount the pipeline near the crossing, they had been welded on the Pucka Island, launched and transported by tugs to the site. In the case of the shorter section the whole pipe was pulled out of water and placed on rollers. The longer section was almost entirely pulled directly from the canal. It is worth noticing that it was the first in Poland installation of such a large polyethylene pipe transported and mounted almost completely from water. The pipelines were founded at the level of Pucka Island between March and April 2007. 620 m and 626 m long pipes were installed, breaking a new European record in the length of a large-dimension pipeline pulled into an HDD drill.
Projektin tiedot
Projektin tiedot
Yhteistyössä mukana
Contractor:
Hydrobudowa 9 .I.B. S.A. from Poznań
Samankaltaisia projekteja
Massiivinen jätevesiviemäri Harjavallasta Poriin
Porin ja Harjavallan välille valmistui massiivinen jätevesien siirtoviemäri.
Kestävyyttä ja laatua tieinfraan Uponor IQ-hulevesijärjestelmällä
Kuokkalaan avattiin marraskuussa 2013 kehäväylä. Väylälle asennettiin 2 kilometriä Uponorin IQ-hulevesiputkea, 250 kaivoa ja 5 kilometriä salaojaputkea.
Vesijohto mökkiläisille vesiosuukunnan turvin
Turvallista, nopeaa ja helppoa
Nyt on NOPEAA
Palojätevedet turvallisesti talteen
Saneeraukset sujumaan
Hyvä on harjuksen hyppiä puhtaassa Ounasjoessa
Parempaa pohjavettä
Lämmitettävät putket takaavat sammutusveden
Euroopan suurin muovinen tierumpu Norjaan
Hulevedet talteen
Weholitesta ilmastussäiliö Iisalmeen
Kurikka sujuttaa vanhat viemärilinjat
Antaa sataa vaan
Puhdasta juomavettä 17 000 partiolaiselle
Virtausmittaus paljastaa vesijohtoverkoston vuodot
Uponorin uusin järjestelmä, Ultra Double, korvasi Raahen vanhan betoniputken
Ympäristöystävällistä lämmitystä ja vedenkäsittelyä Launosten päiväkodissa
Hybridiratkaisuja hulevesien hallintaan
Helppo ja luotettava hulevesiratkaisu
Hulevedet ja epäpuhtaudet fiksusti haltuun
Suoraa hyötyä kaarista
Lahti Energia käyttää työmaillaan ensimmäisenä Suomessa kaariputkia. Kokemukset ovat olleet erittäin hyviä.
Lahden Vipusenkadulla uusittiin kaukolämpöverkkoa. Kaivantoon on laskettu isoja kahdentoista ja kuudentoista metrin DN 300 -putkia. Hitsaajat ovat ryhtymässä töihin. Jokin jää kuitenkin askarruttamaan ohikulkijan mieltä.
Samaan aikaan toisaalla, keskustasta Launeelle johtavalla kaukolämpölinjalla operoidaan hieman tuhdimpien DN 400 -putkien kanssa. Täälläkin sama juttu. Aivan kuin kaikki putket eivät olisi ihan suoria?
Hulevedet haltuun helposti ja nopeasti
Kajaanissa sujuu, kun sujutetaan
Iisalmen Vesi saneerasi runkolinjan sujuttamalla
Tuplasti varmuutta Pohjavesialueelle
Turvallinen juomavesiverkko entiselle teollisuusalueelle
Plastic ensures condensation-free ventilation at new hospital and research facility
Pump structure secures stormwater system’s long life
Drinking water passing through contaminated area in Thisted
Intake pipeline for seawater in Copenhagen Harbour
Butt welding by night of 900 mm pipes ensures stable operation of a district cooling solution in Copenhagen Harbour.
TV-Tower, Estonia
Secure tunnel trunk lines
Weholite limits overflows and pollution in London
Fighting against an ecological disaster in a world-record time
Rapid action was critical when a sewage collector broke in Warsaw, Poland, causing a massive waste spill into the Vistula River. Uponor Infra’s crew worked 24 hours a day in order to stop the pollution of the river. A temporary pipeline was produced, delivered and connected in just eight days.
Collectors for sewage treatment plant
Renovation of reinforced concrete sewer - relining method
Sewage retention chanel
Renovation of cast iron water supply pipeline - swagelining
Thanks to swagelining technology, it was possible to carry out most of the water line modernisation works in the centre of the city of Łódź, in a built-up area, along traffic lanes with heavy traffic of motor vehicles and trams.
Sea outlet - discharge of stream water into the Gdańsk Bay part 2
Renovation of damaged stoneware collector – cracking/short relining
Sewage separation system
Construction of storm water collectors in Nowe Polkowice is one of the stages of a big investment concerning the drainage of the district.
Sea outlet of treated wastewater
A sea outlet of treated wastewater was initiated in Swarzewo. It is yet another of the many environmentally friendly projects that have recently been carried out in Poland where PE pipes were used.
Uponor pressure pipe system Profuse in Borås town
Uponor Infra culverts in major investment at Skåne University Hospital in Malmö
A test installation of an infra culvert with great potential
Strong, Safe and Flexible
Innovative, reliable - and installed in 11 days
Uponor soil drainage system Ultra Rib 2 in Kungälv
Infratunnel protects pipes and cables in new residential area
Focus on sustainability
Weholite installed in Valdemarsvik Sweden
Uponor Vault cleans the storm water
Flow measurement reveals leaks in the water supply network
Safe and Sustainable
Quick installation in the Konotopa channel
Super-sized cooling
Weholite tanks have multiple uses
Water supply in very demanding terrain in Norway
A smart retention system for an anti-flooding solution
September 2018 saw the launch of the project for a stormwater drainage system in Rzeszów, almost 26 kilometres long, in the residential District of Budziwój, which partially coincides with the floodplain of the River Wisłok. One of the elements of this system is the retention canal. The project, scheduled for delivery by May 2020, will help to finally solve flooding problems which have been plaguing the residents of this region of Poland.