Penstock for hydro power plant, Cieszyn, Poland

Penstock for hydro power plant

Hydropower is the  most popular renewable energy resource in the world with  a 16 percent share in the global energy output and counting. In recent years Poland has seen a rise in the number of hydroelectric projects, mainly small power plants, which utilize local watercourses for the production of clean, cheap energy. Recently, for the first time in Poland, Weholite technology was used for the construction of a penstock (water transmission pipeline) for a new small hydro power plant in the city of Cieszyn.

Projektfakta

Cieszyn, Poland
Industri
Skræddersyede konstruktioner, Industrielle rør
Færdiggørelse: 2012

Uponors rolle

Weholite pipes PE DN2200 mm, SN4 - 510 m. Special T-way fitting DN 2200/2xDN1600 mm

The investment project, worth an estimated 1,2 million euros, included the construction of a small hydro power plant  with a capacity of 0,56 MW, utilizing the drop of the Olza river. Typically, a power plant pipeline or canal is introduced at river curve shortcutting the river’s flow, which results is  greater water drop than would be achievable at a weir. In Poland pipelines are used at large hydroelectric facilities while smaller plants depend on open channels. The key factor for choosing a pipeline for the Cieszyn project was the plant’s location in a city park. The city’s authorities demanded that the design take into consideration and preserve the park’s functionality and esthetics.

The investor carefully considered the choice of material for the pipeline. The technical design listed glassfibre reinforced plastic pipes as the material of choice, however MEW S.A.’s final decision was to use PE-HD Weholite DN 2200 mm piping. The decision was based on the high quality of Weholite technology, flexible terms of service offered by Uponor Infra’s as well as the company’s extensive global experience in hydroelectric projects. Durable, leak-proof and lightweight, Weholite pipes proved the ideal solution to the challenges  of the Cieszyn project. Their low weight as compared to pipes made from traditional materials such as steel, cast iron or concrete, made for easy transportation and installation in a challenging terrain of the city park. Among Weholite’s other qualities one should mention resistance to corrosion, chemicals and damage caused by differential soil settlement. These properties assure exceptional reliability and long-life of an underground pipeline, as well as near zero operating costs.

MEW S.A. also greatly appreciated the smoothness of the pipeline’s inner surface.  Thanks to a low roughness coefficient "k" and monolithic joints of the penstock, as well as forgoing segment bends, energy losses caused by water friction inside the pipeline are reduced to a minimum, which translates into greater energy efficiency of the power plant and greater return on investment.

Construction started in October 2010 when trenches were made for both the powerhouse and the pipeline. The pipes were manufactured in 12,5 m lengths and transported from Uponor Infra’s production plant in Kleszczów to Cieszyn using truck tractors.  In all, between November 2010 and September 2011 Uponor Infra delivered 42 shipments of pipes of total length of 510 m.     

The pipes were laid out on ground level in 50 to 100 m sections and joined by means of extrusion welding. The joined sections were then lowered into the trench and welded together by the Uponor Infra service team, which was responsible for all of the welding work. Extrusion welding provided for a leak-proof and monolithic pipeline and proved very well suited to the demands of winter installation. Weholite’s built-in flexibility also proved extremely useful as it allowed for gentle bending of the pipeline, which made its handling much easier and provided a cost- and time-effective alternative to using segment bends and thrust blocks.

Another great property of Weholite piping is the possibility of prefabricating compound fittings. The final section of the penstock, a tee DN 2200 mm designed to divide the water flow into two  streams, one for each of the two turbines, was produced at the Uponor Infra plant and delivered to project site with the assistance of a pilot car. In May 2011, after intensive construction work the pipeline was secured in the ground and covered with soil. Work on the powerhouse was completed  in June 2011 and in September 2011 collars for joining the pipeline with the turbines were delivered. Hydro power plant  started its commercial operation in January 2012.

Penstock for hydro power plant

Cieszyn 2011 1

Projektinformation

Projektinformation

Land
Poland
Færdiggørelse
2012
Projekttype
Ny bygning
Bygningstype
Industri

Partnere

Partnere

Investor:
MEW S.A. Warszawa

Lignende projekter

Weholite yields savings and smoother implementation

Weholite yields savings and smoother implementation

New dry land fish farm which will produce 3,200 tonnes of rainbow trout annually is being build in Eckerö in the Åland Islands. Uponor Infra has provided design assistance and delivers the pipes and is responsible for their installation and welding.

Record-breaking intake cooling system in the Philippines

Record-breaking intake cooling system in the Philippines

New challenges are where the Project Services Department at Uponor Infra feels most comfortable and can demonstrate its
continuously developing expertise. The aim on this occasion was to provide a seawater intake cooling system – a pipeline, intake structure and chlorination line – for the 420MW extension of the Pagbilao Coal Fired Power Plant on Luzon Island in the Philippines.
Sustainable  solution for  a pulp & paper mill

Sustainable solution for a pulp & paper mill

Weholite’s ability to withstand external wear, such as friction against the seabed, was an important criterion when the outfall pipe of Stora Enso’s pulp and paper mill in Nymölla, southern Sweden, had to be replaced.

 

 

A raw water system for the new power unit

A raw water system for the new power unit

To ensure failure-free operation of a raw water system, a polyethylene-made pipeline (PEHD) with a length of approximately 9 km was installed (in mining damage conditions), of which 3 km uses the trenchless technique – relining.
Stora Enso Nymölla mill biogas facility

Stora Enso Nymölla mill biogas facility

Stora Enso Nymölla Mill in southern Sweden produces pulp- and wood-free uncoated paper and is the second largest paper manufacturing company in Europe. Nymölla Mill belongs to the "Paper" division and has an annual capacity of 340,000 tonnes of pulp and 485,000 tonnes of paper. The mill started in 1962 and has 540 employees. The paper manufactured by Nymölla Mill is recyclable, renewable and biodegradable. Approximately 90% of Nymölla Bruk's paper brands have eco-label certification that certifies the products' reduced environmental impact during the product's life cycle. Paper products from Stora Enso are available all over the world.
 
Record-breaking pipes in Keljonlahti

Record-breaking pipes in Keljonlahti

Construction of the pipe network for cooling water at the Keljonlahti power plant began in December 2008. 3,000/3,300 mm Weholite pipes were selected for the network. The combined length of the entire intake and discharge pipe network for cooling water is 1,714 metres.
Extension of the district cooling station seawater intake in Helsingborg, Sweden

Extension of the district cooling station seawater intake in Helsingborg, Sweden

 The district cooling system in Helsingborg involves the streamlining of current production. By means of seawater and using heat from the district heating network to power an absorption cooling unit, district cooling provides much better environmental values than electric cooling units. The district cooling station is an efficient source of cooling for buildings, industrial facilities and shopping centres.

 

Fish farming with the smallest possible footprint

Fish farming with the smallest possible footprint

Andfjord Salmon AS, a Norwegian fish farming company, has the ambition to create a sustainable, environmentally and fish-friendly onshore facility – with the smallest possible footprint. This patented facility combines the best from both traditional ocean net-pens and land-based salmon farming. The intake and outfall lines are built with highly durable Weholite PE pipes and panels with a 100-year life span.