Weholite yields savings and smoother implementation, Eckerö, Finland
Weholite yields savings and smoother implementation
The Åland Islands-based company Fifax Ab is currently building one of the largest fish farms in the Nordic countries. The aboveground facility is located in Eckerö, Åland, about 1.8 kilometres from the sea. Operating at full capacity, it will produce more than 3,200 tonnes of rainbow trout for the Finnish and Scandinavian markets annually. The facility piping contract was simplified and implemented at a lower cost by replacing the pressure pipes specified in the original plan with 1,800mm Weholite pipes.
Projektfakta
Uponors rolle
The dry land facility under construction in the Åland Islands – an archipelago in the Baltic Sea and Finland’s only autonomous region – will be one of the most advanced fish farms in the Nordic countries from an environmental perspective. It will be the first such facility in the Baltic region to recycle its utility water: it will not discharge water and fish nutrients into the sea.
This ecologically designed facility employs a closed recirculating aquaculture system and provides fish with ideal growth conditions. Unlike when raising fish in natural waters, the fish do not need to be fed antibiotics. It is also easier to monitor the feeding of the fish, thereby preventing overfeeding. This saves both the environment and costs. The plant is priced at about EUR 18 million and will be one of the largest dry land fish farms in the Nordic countries. The facility takes care of the process from beginning to end, from fish egg production to fish processing.
The building will measure about 15,000m2 with three basin areas. A total of 36 five metre-deep basins with a diameter of 12 metres will be built. The water used by the facility will be pumped from the Sea of Åland, located 1.8km away, to three water treatment plants.
In addition to its own water treatment plants, a biogas plant will be built in the area. It will utilise organic waste from fish processing to produce gas for use in the operations of the facility.
Revised design yields savings
Uponor Infra has been involved in the project since the design phase and will carry out the piping works required and the delivery and installation of pipes. Following the recommendation of Uponor Infra’s experts, the original plans for the piping contract were revised to achieve a solution that yields greater cost-efficiency. Dan Engblom, a consultant at Deab Konsult who is responsible for the foundation and piping works in the project, says that the changes reduced the costs by about a third, compared to the original plans.
It was originally intended for the facility pipe system to be built with 630–800mm pressure pipes. “Uponor Infra recommended that the pipes be changed to 1,800mm diameter low-pressure pipes, which stand up well to the 0.5 bar pressure in the system.”
Thanks to Weholite, the crisscrossing pipes specified in the original plans could also be simplified. In the solution now being constructed, the recirculating aquaculture system in each of the three basin areas is being implemented with two Weholite pipes connected to the fish tanks.
“This solution is simpler, more rational and substantially cheaper,” says Dan Engblom.
“Weholite pipes with a diameter of as much as 3.5 metres can be used to produce end-to-end pipe and tank systems as well as a variety of customised solutions,” says Tom Karnela, Sales Manager at Uponor Infra.
With their layered construction, Weholite pipes are durable, flexible and light. They are manufactured from polyethylene (PE) or polypropylene (PP) profile using spiral seams.
Harnessing experience yields benefits
The three-stage pipe installation work began at the turn of March and April. First-stage testing was carried out at the end of July, after which fish farming has been gradually started up. The whole pipe installation contract is expected to be completed at the turn of the year.
Engblom, who is responsible for overseeing the piping works, is satisfied with the progress of the work. “Pipe installation has progressed extremely well. Furthermore, Uponor’s pipe deliveries are flexible, which has facilitated the organisation of work at the installation site.”
According to Tom Karnela, this project is a good example of why one should turn to Uponor’s experts in the early stage of projects. “When we come on board early, we can ensure that the customer reaps the best benefits from our expertise and is satisfied with the completed project.” Uponor Infra is delivering more than 10 kilometres of different kinds of pipes and other materials for the Fifax facility. The production facility is being delivered by the Norwegian company AKVA Group, the world’s leading producer of aquaculture technology.Projektinformation
Projektinformation
Partnere
Deab Konsult
P +358 40 526 5467
Installation:
Uponor Infra Oy
P +358 20 129 211
Lignende projekter
Uponor leverer tanke til industrielt udviklingsprojekt på Vestforbrænding
Aalborg Havn bygger på bæredygtige spildevandsrør
A durable and reliable solution for wastewater
Record-breaking intake cooling system in the Philippines
continuously developing expertise. The aim on this occasion was to provide a seawater intake cooling system – a pipeline, intake structure and chlorination line – for the 420MW extension of the Pagbilao Coal Fired Power Plant on Luzon Island in the Philippines.
Sustainable solution for a pulp & paper mill
Weholite’s ability to withstand external wear, such as friction against the seabed, was an important criterion when the outfall pipe of Stora Enso’s pulp and paper mill in Nymölla, southern Sweden, had to be replaced.
Power boost for Stockholm’s district heating network
A raw water system for the new power unit
Transport of brine - technological pipelines
The technological pipelines transporting the brine washed out during the construction of underground gas storage facility followed by its discharge into the Puck Bay.
Penstock for hydro power plant
Weholite technology was used for the construction of a penstock (water transmission pipeline) for a new small hydro power plant in the city of Cieszyn.
Transport of brine - renovation of technological pipelines
Transport of slurry supernatants – process pipelines, KGHM
Drainage systems around Żelazny Most tailings pond, KGHM
For almost 20 years, Uponor Infra has assisted the Polish mining conglomerate KGHM Polska Miedź S.A. in modernising Europe’s largest tailings pond.
Transport of post-flotation waste – process pipelines, KGHM
For many years Uponor Infra has suppplied KGHM with high-quality polyethylene piping systems that transport water and slurry.
Brown coal mine drainage systems
Uponor Infra has been delivering for the last dozen or so years the PEHD systems for surface drainage of brown coal mine
Drainage system for heat and power station
Slotted drainage VipLiner module made by Uponor Infra has been chosen to build a drainage system for heat and power station of Gdynia.
A new generation biotechnology factory
Extension of the district cooling station seawater intake in Helsingborg, Sweden
The district cooling system in Helsingborg involves the streamlining of current production. By means of seawater and using heat from the district heating network to power an absorption cooling unit, district cooling provides much better environmental values than electric cooling units. The district cooling station is an efficient source of cooling for buildings, industrial facilities and shopping centres.