Hydrotechnical investments are complex and advanced engineering projects, carried out in difficult soil and water conditions. That is why it is so important to choose experienced contractors and proven materials for their implementation. In the case of this investment, the contractor of the works is POM Krapkowice, and the supplier of materials for the construction of the double line of the siphon culvert is Uponor Infra - a company with over 70 years of experience in the production of PE and PP pipe systems. Uponor Infra is known for the implementation of technically advanced engineering projects. She has participated in many prestigious investments, often record-breaking in terms of the parameters of the pipes used. For the investment in Krapkowice, the company supplied Weholite PE100 DN2000 SN8 pipes with a length of 186.4 m, as well as large-size special fittings and segmented bends.
Polyethylene pipelines are completely resistant to corrosion, fouling and chemical factors, including changing pH of water and soil. Light elements are easy to unload and install. Thanks to their flexibility and perfect cooperation with the ground, they are resistant to terrain impact, which is why they can be used in difficult ground and water conditions, as well as in floodplains and areas of mining damage up to category IV inclusive. Excellent material properties of polyethylene pipes and assembly of elements by extrusion welding is a guarantee of 100% tightness of the system and transfer of all axial forces. The method ensures a homogeneous connection, full control and a high safety margin in the case of difficult working conditions. As a result, the service life of pipelines exceeds even 100 years.
The double line of the siphon culvert was installed under the bottom of the Oder River using the open trench method. The connection of the pipeline sections was made by the Uponor Infra service group using the WL-3000 automatic extrusion welding machine. The scope of works related to the siphon culvert included the construction of sheet piling, excavations in the cofferdam, construction of the foundation, laying of pipelines with manholes and construction of the inlet abutment to the culvert and the outlet of the culvert.
Completion of the investment at the Krapkowice barrage is planned for the third quarter of 2023.