Uponor
Fallstudie

Transport of post-flotation waste – process pipelines, KGHM, Poland

Transport of post-flotation waste – process pipelines

KGHM Polska Miedź SA – is one of the largest copper and silver producers in the world. The raw materials base of KGHM Polska Miedź S.A. includes the copper ore deposit, which is the largest in Europe and one of the biggest in the world. The mining areas of the size of approx. 470 km2 were created for the purpose of its mining.

Projektfakta

Poland
Industrimark
Designade lösningar, Processvattensystem
Färdigställt: 2021

Uponors roll

WehoPipe pipes DN 125, 180, 225, 315, 450, 500, 710, 800, 900, 1000, 1100, 1200, 1300, 1370 PN7,5-PN20 - a total of approx. 41,5 km of pipeline

KGHM has in place its own integrated production structure, which includes three mines (ZG „Lubin”, ZG „Rudna”, ZG „Polkowice-Sieroszowice”), three copper smelters („Głogów", „Legnica”, „Cedynia”), and branches supporting the core activity (Ore Enrichment Facilities. Hydrotechnical Facility). The Hydrotechnical Facility is responsible for storage and management of the waste created during the production process. The basic tasks of the Facility are related to the water-sludge management of three Ore Enrichment Facilities, which conduct the copper ore mining output enrichment operations  under a flotation method. The post-flotation waste is a slurry, which is transported via pipelines to Żelazny Most tailings pond. The solid phase sedimentation process takes place at the storage facility and the cleaned water is collected and re-directed to the Ore Enrichment Facilities.

Beginning of cooperation

The first deliveries of PEHD pipelines for slurry transport - d.800 PN12,5 – were executed by Uponor Infra (former KWH Pipe) in 2000. PBH Odra 2 was the contractor in this investment. This investment concerned crossing of the over under the submerging method. The length of the submerged section was 168 m.

Another interesting investment executed at Hydrotechnical Facility concerned the delivery of pipelines d.710mm SDR17,6 for Pebeka S.A. This investment concerned renovation of steel slurry pipeline d.813mm with the use of PEHD pipe under the long relining method. The longest section of the pipeline inserted under a single operation was 1000m.This was a record, which allowed the Contractor to receive Limbur award in category: Project of year 2002 - Renovation.

Polyethylene proven in harsh environments

In 2008, Uponor Infra took part in an interesting modernisation project involving an existing polyethylene pipeline, which had to be replaced due to an increase in slurry production. The DN/OD 500 mm pipeline was replaced by a new 2.5 km double DN/OD 900 mm pipeline and installed above ground level on existing steel supports. When KGHM inspected the dismantled, 10 year-old pipeline, it found that the pipe bore little signs of use. Paweł Pill of Uponor Infra, project manager in the Industrial Sales Department, who was present at the inspection, confirms that the pipeline was as good as new, with no visible signs of wear. “Even the inner welding beads were intact while in the same period of time the steel and concrete pipelines experienced numerous glitches,” he says. This proved that polyethylene is the optimal choice for conveying highly abrasive mining waste at KGHM.

Further investments – futher kilometres of pipes

The biggest investment at Hydrotechnical Facility was executed jointly with Tolos from Żory in 2009. It concerned laying of the double line of PEHD pipelines of following parameters:

  • d.1000 SDR11 PN16 - approx. 2,5km
  • d.1000 SDR21 PN8 - approx. 1km
  • d.1300 SDR17 PN10 - approx. 2km
  • d.1370 SDR17 PN10 - approx. 1,4km

Investment executed during the years 2014-2015 included the delivery of pipelines d.1250 SDR17 PN10 (approx. 1,5 km) and d.1290 SDR13,6 PN12,5 (approx. 3km).

Versatility of the PE-HD technology

KGHM Polska Miedź S.A. is a company operating on a huge scale, and as such it expects efficiency, innovation and top technological solutions. The projects carried out over the years by Uponor Infra and Hydrotechnical Facility confirm the highest quality and versatility of the PE-HD technology. Uponor Infra has proven itself to be a reliable partner, ready to listen and assist in making even the most demanding engineering projects work.

 

Transport of post-flotation waste – process pipelines

KWHM poflotacyjny 2015 1

Projektinformation

Projektinformation

Land
Poland
Färdigställt
2021
Projekttyp
Renovation
Byggnadstyp
Industrimark

Samarbete

Samarbete

Investor:
KGHM Polska Miedź S.A.

Contactors:
PBH ODRA 2
PeBeKa S.A. - Lubin
PPHU Zachód Sp. z o.o. – Polkowice
P.P.U. „MONT -INSTAL” Sp. z o.o. – Polkowice
Arkop Sp. z o.o. - Wrocław
P.B.M TOLOS Sp.J.- Żory

Liknande projekt

En hållbar lösning för ett massa- och pappersbruk

En hållbar lösning för ett massa- och pappersbruk

Att inte använda utvändiga betongvikter var av mycket stort intresse för Nymölla eftersom de inte kunde hantera installationen av utloppsledningen själva och att arbetet kunde utföras på installationsplatsen av Uponor Infra Projektservice, var avgörande faktorer för Nymölla i val av ledning.


 

 

Stora Enso Nymölla biogasanläggning

Stora Enso Nymölla biogasanläggning

Stora Enso Nymölla Bruk i södra Sverige tillverkar massa- och träfritt obestruket papper och är det näst största papperstillverkningsföretaget i Europa. Nymölla Bruk tillhör divisionen ”Paper” och har en årlig kapacitet på 340 000 ton massa och 485 000 ton papper. Bruket startade 1962 och har 540 anställda. Pappret tillverkat av Nymölla Bruk är återvinningsbart, förnybart och biologiskt nedbrytbart. Cirka 90 % av Nymölla Bruks pappersvarumärken har miljömärkescertifiering som intygar produkternas minskade miljöpåverkan under produktens livscykel. Pappersprodukter från Stora Enso finns i hela världen.
 
Weholite yields savings and smoother implementation

Weholite yields savings and smoother implementation

New dry land fish farm which will produce 3,200 tonnes of rainbow trout annually is being build in Eckerö in the Åland Islands. Uponor Infra has provided design assistance and delivers the pipes and is responsible for their installation and welding.

Record-breaking intake cooling system in the Philippines

Record-breaking intake cooling system in the Philippines

New challenges are where the Project Services Department at Uponor Infra feels most comfortable and can demonstrate its
continuously developing expertise. The aim on this occasion was to provide a seawater intake cooling system – a pipeline, intake structure and chlorination line – for the 420MW extension of the Pagbilao Coal Fired Power Plant on Luzon Island in the Philippines.
A raw water system for the new power unit

A raw water system for the new power unit

To ensure failure-free operation of a raw water system, a polyethylene-made pipeline (PEHD) with a length of approximately 9 km was installed (in mining damage conditions), of which 3 km uses the trenchless technique – relining.
Record-breaking pipes in Keljonlahti

Record-breaking pipes in Keljonlahti

Construction of the pipe network for cooling water at the Keljonlahti power plant began in December 2008. 3,000/3,300 mm Weholite pipes were selected for the network. The combined length of the entire intake and discharge pipe network for cooling water is 1,714 metres.
Fish farming with the smallest possible footprint

Fish farming with the smallest possible footprint

Andfjord Salmon AS, a Norwegian fish farming company, has the ambition to create a sustainable, environmentally and fish-friendly onshore facility – with the smallest possible footprint. This patented facility combines the best from both traditional ocean net-pens and land-based salmon farming. The intake and outfall lines are built with highly durable Weholite PE pipes and panels with a 100-year life span.