Transport of brine - technological pipelines, Kosakowo, Poland

Transport of brine - technological pipelines

The extension of underground gas storage facilities is very important from the perspective of Poland’s gas security and thus for a number of years has been one of investment priorities of PGNiG. KPMG Kosakowo is the first underground methane-rich content gas storage facility in northern Poland constructed in rock salt bed. The gas will be stored in adapted salt chambers at the depth of 1000 to 1200 m. The completion of the entire investment is planned for 2020 and as of 2014 it will be operating with capacity of 100 million m3.

Projektfakta

Kosakowo, Poland
Industrimark
Processvattensystem
Färdigställt: 2009

Uponors roll

WehoPipe pipes PE100 SDR 11 PN16 DN355 – a total length of 6 km, including land part - 3,7 km, sea part - 2,3 km

The construction of target ten storage chambers of total capacity of 250 million m3 will involve excavation of 3.4 million tones of salt in the form of a brine of approx. 18 million m3 volume. The storage chambers are created by salt leaching with the use of water pumped into the salt bed. This process results in the formation of a brine, which should be managed or discharged in a safe manner into the reservoir.

As of 2010 this brine is discharged through pipeline WehoPipe PE DN 355 into the Puck Bay. A system of diffusers was installed in the distance of 2.3 km from the shore at 8m depth, which allows to control the distribution of the brine in the Puck Bay waters. The current failure-free operation of the brine pipeline confirms the suitability of PE system to such demanding and high-level applications.

Transport of brine - technological pipelines

Kosakowo referece Uponor Infra

Projektinformation

Projektinformation

Land
Poland
Färdigställt
2009
Projekttyp
Nybyggnation
Byggnadstyp
Industrimark

Samarbete

Samarbete

Investor:
PGNiG S.A.
General contractor:
INVESTGAS (now Operator Systemu Magazynowania Sp z o.o.)

Liknande projekt

En hållbar lösning för ett massa- och pappersbruk

En hållbar lösning för ett massa- och pappersbruk

Att inte använda utvändiga betongvikter var av mycket stort intresse för Nymölla eftersom de inte kunde hantera installationen av utloppsledningen själva och att arbetet kunde utföras på installationsplatsen av Uponor Infra Projektservice, var avgörande faktorer för Nymölla i val av ledning.


 

 

Stora Enso Nymölla biogasanläggning

Stora Enso Nymölla biogasanläggning

Stora Enso Nymölla Bruk i södra Sverige tillverkar massa- och träfritt obestruket papper och är det näst största papperstillverkningsföretaget i Europa. Nymölla Bruk tillhör divisionen ”Paper” och har en årlig kapacitet på 340 000 ton massa och 485 000 ton papper. Bruket startade 1962 och har 540 anställda. Pappret tillverkat av Nymölla Bruk är återvinningsbart, förnybart och biologiskt nedbrytbart. Cirka 90 % av Nymölla Bruks pappersvarumärken har miljömärkescertifiering som intygar produkternas minskade miljöpåverkan under produktens livscykel. Pappersprodukter från Stora Enso finns i hela världen.
 
Weholite yields savings and smoother implementation

Weholite yields savings and smoother implementation

New dry land fish farm which will produce 3,200 tonnes of rainbow trout annually is being build in Eckerö in the Åland Islands. Uponor Infra has provided design assistance and delivers the pipes and is responsible for their installation and welding.

Record-breaking intake cooling system in the Philippines

Record-breaking intake cooling system in the Philippines

New challenges are where the Project Services Department at Uponor Infra feels most comfortable and can demonstrate its
continuously developing expertise. The aim on this occasion was to provide a seawater intake cooling system – a pipeline, intake structure and chlorination line – for the 420MW extension of the Pagbilao Coal Fired Power Plant on Luzon Island in the Philippines.
A raw water system for the new power unit

A raw water system for the new power unit

To ensure failure-free operation of a raw water system, a polyethylene-made pipeline (PEHD) with a length of approximately 9 km was installed (in mining damage conditions), of which 3 km uses the trenchless technique – relining.
Record-breaking pipes in Keljonlahti

Record-breaking pipes in Keljonlahti

Construction of the pipe network for cooling water at the Keljonlahti power plant began in December 2008. 3,000/3,300 mm Weholite pipes were selected for the network. The combined length of the entire intake and discharge pipe network for cooling water is 1,714 metres.
Fish farming with the smallest possible footprint

Fish farming with the smallest possible footprint

Andfjord Salmon AS, a Norwegian fish farming company, has the ambition to create a sustainable, environmentally and fish-friendly onshore facility – with the smallest possible footprint. This patented facility combines the best from both traditional ocean net-pens and land-based salmon farming. The intake and outfall lines are built with highly durable Weholite PE pipes and panels with a 100-year life span.